FS#138 - Adding a new holiday does not affect to the schedule

Attached to Project: Project Planner HD
Opened by Chiaki Kono (Gantt) - Thursday, 19 September 2013, 21:03 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Tuesday, 08 October 2013, 11:40 GMT+2
Task Type Bug Report
Category Backend / Core
Status Closed
Assigned To Tomasz Wojtkowiak (TomekW)
Operating System All
Severity Low
Priority Normal
Reported Version 2.1.2
Due in Version 2.2.1
Due Date Undecided
Percent Complete 100%
Votes 0
Private No

Details

For example: There is a 3 days task (named "A") staring from 10/1/2013 and ending at 10/3/2013. I made 10/2/2013 as holiday using calendar edit, which means no work day. I expected that the end date of the task "A" would change to 1-/4/2013, but it did not change, still it is 10/3/2013.
This task depends upon

Closed by  Tomasz Wojtkowiak (TomekW)
Tuesday, 08 October 2013, 11:40 GMT+2
Reason for closing:  Fixed
Additional comments about closing:  Fixed in 2.2.1