FS#85 - Summary task linked to child tasks
Attached to Project:
Project Planner iPhone
Opened by tone (ffctone) - Tuesday, 06 December 2011, 12:03 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Wednesday, 14 November 2012, 14:18 GMT+2
Opened by tone (ffctone) - Tuesday, 06 December 2011, 12:03 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Wednesday, 14 November 2012, 14:18 GMT+2
|
DetailsThe summary task need to be linked to those tasks that relate directly to them, as they do in MS projects for example.
example Summary task (proposal) task 1: scope duration 2 days task 2: write proposal 4 days in this case the summary task should automatically default to 4 days the longest path on that element and if the tasks are linked then it should default to 6 days 2+4=6 at the moment the summary task duration has to be manally entered which is just very poor |
This task depends upon
Closed by Tomasz Wojtkowiak (TomekW)
Wednesday, 14 November 2012, 14:18 GMT+2
Reason for closing: Implemented
Wednesday, 14 November 2012, 14:18 GMT+2
Reason for closing: Implemented