FS#138 - Adding a new holiday does not affect to the schedule
Attached to Project:
Project Planner HD
Opened by Chiaki Kono (Gantt) - Thursday, 19 September 2013, 21:03 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Tuesday, 08 October 2013, 11:40 GMT+2
Opened by Chiaki Kono (Gantt) - Thursday, 19 September 2013, 21:03 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Tuesday, 08 October 2013, 11:40 GMT+2
|
DetailsFor example: There is a 3 days task (named "A") staring from 10/1/2013 and ending at 10/3/2013. I made 10/2/2013 as holiday using calendar edit, which means no work day. I expected that the end date of the task "A" would change to 1-/4/2013, but it did not change, still it is 10/3/2013.
|
This task depends upon
Closed by Tomasz Wojtkowiak (TomekW)
Tuesday, 08 October 2013, 11:40 GMT+2
Reason for closing: Fixed
Additional comments about closing: Fixed in 2.2.1