FS#26 - ability to enter task duration in calendar days
Attached to Project:
Project Planner iPhone
Opened by Nils (nilsa) - Tuesday, 28 September 2010, 23:11 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Thursday, 30 December 2010, 18:43 GMT+2
Opened by Nils (nilsa) - Tuesday, 28 September 2010, 23:11 GMT+2
Last edited by Tomasz Wojtkowiak (TomekW) - Thursday, 30 December 2010, 18:43 GMT+2
|
DetailsWhen I enter a new task by duration in days I would like to be able to specify that the duration constitutes calendar days.
As it is now it does it by work/week days skipping over weekends. |
This task depends upon
Closed by Tomasz Wojtkowiak (TomekW)
Thursday, 30 December 2010, 18:43 GMT+2
Reason for closing: Implemented
Thursday, 30 December 2010, 18:43 GMT+2
Reason for closing: Implemented
To do this go to Preferences -> Default Calendar and check/ uncheck working days in the week. You can also add holidays.
If you would like to change calendar for specific project, you can do it on project window -> Project -> your project -> calendar.